EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Work Type: Construction Work
Phase: Construction
Limits: Sextant Drive to Port Comfort Road
City:
County:
Road:
Start of Current Phase: Late 2022
About

Thank you for helping us to celebrate substantial completion of
the Sanibel Causeway Emergency Restoration and
the opening of Lee County's Punta Rassa Boat Ramp!

Project Information:

On October 5, 2022, the Florida Department of Transportation’s (FDOT) contractors mobilized to complete emergency repairs to the Sanibel Causeway.  After only six days, the project team was able to expedite repairs and lead a convoy of utility restoration teams and equipment across the Sanibel Causeway. On October 19, just three weeks after Hurricane Ian washed away the land and roadway connecting the mainland to Sanibel and Captiva Islands, and a week ahead of schedule, FDOT opened the bridge to first responders, utility crews, contractors and residents. 

The project team put an extraordinary amount of manpower and materials into the project to ensure all road lanes on the causeway were open for the Christmas holidays in 2023 – 15 months after Hurricane Ian had destroyed access to Sanibel. Every member of this project team took great personal pride in getting the roadway open for the 2023 holidays.

This project reconstructed the roadway to standards and specifications, constructed permanent bridge approaches, and restored drainage, lighting, pavement markings, as well as provided access for utility service along the causeway islands. Support has been given to protect the natural environment from corroding shorelines while meeting the community’s needs such as safe recreational areas for residents and visitors to enjoy the beaches.  Please click on the links below listed under Proposed Resiliency Measures in the Project Documents section of this page for more information.

Hurricane Ian forever changed the landscape of the Sanibel Causeway, simply because the storm shifted sands from the islands. FDOT reconstructed the Sanibel Causeway using a more resilient design, while returning the Causeway to the pre-storm condition to the maximum extent possible. 

Public Involvement
View Factsheet
Contact Information
Communications Team
Jennifer Dorning
239-338-7723
Jennifer.Dorning@dot.state.fl.us
For Media Inquiries Only
fdot-d1comm@dot.state.fl.us
RoadWatch
  • Sanibel Causeway Emergency Restoration: Reduced speed limits remain enforced east of the toll plaza. Pedestrians are not permitted on the Sanibel Causeway.  

    The following work activities above are scheduled to occur, however unforeseen underground conditions and weather may affect this schedule. 

    • The Punta Rassa Boat Ramp is now open to the public with limited amenities, including the ramp, partial docks, parking and restrooms. Lighting work continues at the toll plaza.  Crews must utilize the Punta Rassa parking area, reducing the number of boat parking spaces.  Please use caution as construction vehicles and crews are present.  

     

    • The contractor is installing sod and signage east of the toll plaza. 

     

    All users are urged to be courteous and pay attention as bicyclists share the road on the Causeway and vehicles are entering and existing at public beach access points of the Causeway Islands Park. Visitors may check www.leegov.com/parks for updates on amenities. 

Project Documents
Project Images
August 2025 Ribbon Cutting
August 2025 Ribbon Cutting
August 2025 Ribbon Cutting
August 2025 Ribbon Cutting
August 2025 Ribbon Cutting
August 2025
August 2025
August 2025
August 2025
August 2025
August 2025
August 2025
August 2025
May 2025
May 2025
May 2025
May 2025
May 2025
May 2025
May 2025
May 2025
May 2025
May 2025
March 2025 Shoulder Work
March 2025 Placing Sod
March 2025 Aerial View
March 2025 Guardrail
March 2025 Placing Concrete
March 2025 Paving
March 2025 Paving
February 2025 Installing Guardrail
February 2025 Installing Guardrail
February 2025 Placing Asphalt
February 2025 Grading Swale
February 2025 Sod Placement
February 2025 Paving
February 2025 Paving
February 2025 Toll Booth Sidewalk
February 2025 Curb Gutter
February 2025 Island Beach Parking
February 2025 Median Barrier
January 2025 Removing Temporary Asphalt
January 2025 Grading Median
January 2025 Drainage Pipe Repair
January 2025 Paving
January 2025 Pipe Backfill
January 2025 Grading Pond
January 2025 Storm Drain Installation
January 2025 Installing Marine Mattresses
January 2025 Armor Stone Placement
January 2025 Excavation for Marine Mattresses
January 2025 Backfilling Drainage
January 2025 Placing Armor Stone
January 2025 Installing Marine Mattresses
December 2024 Installing Manatee Grates
December 2024 Compacting Embankment
December 2024 Installing Endwall Steel
December 2024 Cap Form
December 2024 Cap Form
December 2024 Pipe Installation
December 2024 Underdrain
November 2024 Paving
November 2024 Installing New Drainage Pipes
November 2024 Installing Drainage Pipes
November 2024 Excavating
November 2024 Excavating
November 2024 Pouring Drainage Footer
November 2024 Sweeping Base
November 2024 Paving
November 2024 Removing Sand for Junction Slab
November 2024 Removing Sand for Junction Slab
November 2024 Sheet Pile Install
November 2024 Tying Rebar
November 2024 Utility Work
November 2024 Pond Grading
November 2024 Parking Posts
November 2024 Parking Posts
November 2024 Placing Sod
October 2024 Removing Temporary Plates
October 2024 Removing Sheet Piles
October 2024 Prepping for Ditch Pavement
October 2024 Building Wall
October 2024 Backfilling
October 2024 Forming Shear Block
October 2024 Pouring Ditch Pavement
October 2024 Compacting
October 2024 Shear Block
October 2024 Shoulder Sod
October 2024 Shoulder Sod
October 2024 Boat Ramp Form Work
October 2024 Beach Embankment
September 2024 Setting Drainage Pipes
September 2024 Setting Drainage Pipes
September 2024 Cutting Drainage
September 2024 Pouring Junction Slab
September 2024 Headwall Footing
September 2024 Drainage Footing
September 2024 Pouring Junction Slab
August 2024 McGregor Boulevard Pipe Crossing
September 2024 Armor Stone Installation
September 2024 Sewall Cap Concrete Placement
August 2024 Marine Mattress Guide Rod Installation
August 2024 Dewatering Cofferdam
August 2024 Dewatering Cofferdam
August 2024 Backfill Pipe Penetration
July 2024 Fascia Wall
July 2024 Armor Stone
July 2024 Pipe Installation
July 2024 Bridge Pile Removal
July 2024 Marine Mattress Concrete Closure Pour
July 2024 Marine Mattress Concrete Closure Pour
June 2024 Setting Drainage
June 2024 Marine Mattress Backfill
June 2024 Armor Stone Placement
June 2024 Concrete Placement
June 2024 Fascia Wall
June 2024 Setting Drainage
June 2024 Armor Stone Installation
June 2024 Paving Wedge
June 2024 Demoing Existing Drainage Structure
June 2024 Excavating for Marine Mattress Placement
June 2024 Marine Mattress Placement
June 2024 Fascia Wall Concrete Placement
May 2024 Seawall Closure Concrete Pour
May 2024 Armor Stone Placement
May 2024 Excavation for Marine Mattresses
May 2024 Marine Mattress Installation
May 2024 Median Barrier Wall Concrete Placement
May 2024 Fascia Wall Placement
May 2024 Placement of Concrete
Apr 2024 Concrete Cap Placement
Apr 2024 Placement of Concrete Cap
Apr 2024 Marine Mattress Installation
Apr 2024 Excavation in Preparation for Armor Stone Placement
Jan 2024 Island B
Jan 2024 Island A
Jan 2024 Bridge from Mainland
Dec 2023 Road Opens Two Way Traffic
Dec 2023 Securing Island Wall Cap Framework
Nov 2023 Finishing Concrete on New Bridge Approach
Nov 2023 Pouring Concrete for New Bridge Approaches
Nov 2023 Lowering Reinforcing Rebar Into Place
Nov 2023 Preparing to Excavate Temp Bridge Approaches
Oct 2023 Temp Road with New Road Visible
Oct 2023 New Road Surface Next to Capped Island Walls
Oct 2023 Loading Rip Rap on Barges
Oct 2023 Securing King Pile Sheets
Oct 2023 Installing Drainage System
Oct 2023 Placing Armor Stone
Sept 2023 Driving King Pile into Place
Sept 2023 Moving Marine Mattress to Staging Area
Sept 2023 Hand Tying Matresses Shut
Sept 2023 Filling Marine Mattresses
Sept 2023 Finishing Island Wall Caps
Sept 2023 Extruding Concrete into Island Wall Cap Frames
Sept 2023 Retaining Wall in Place against the Bridge
Sept 2023 Armor Stone Delivery
July 2023 Installing Island Walls
May 2023 Installing Retaining Walls
Temporarily restored Sanibel Causeway
Sanibel Causeway - post Hurricane Ian
Sanibel Causeway - post Hurricane Ian
Sanibel Causeway - post Hurricane Ian
Sanibel Causeway - post Hurricane Ian
Sanibel Causeway - post Hurricane Ian