(Dates are tentative and subject to change.)

Financial Project ID: 420613-2-32-01
Design of I-75 / Fruitville Road Interchange
Length: 2 miles

Plans Production

Phase I June 2017
Phase II June 2018
Determine Final ROW Requirements September 2018
Phase III Late 2019
Phase IV Late 2020
Final Early 2021
ROW Acquisition Phase Underway
Construction Not currently funded