Project Details
Work Type: Widening
Phase: Construction
Limits: from US 41 to I-75
Length: 5 miles
County:
Road:
Construction Cost: $47.5 million
Start of Current Phase: Early 2022
Est. Completion of Current Phase: Early 2025
About

The Florida Department of Transportation (FDOT) District One is conducting a Design-Build project to widen River Road from north of US 41 to south of I-75. The project limits fall within Sarasota County. The project length is approximately 5.06 miles. A Project Development & Environmental (PD&E) Study was completed to examine environmental impacts and opportunities for mitigation. The project will widen the roadway from two lanes to six lanes between US 41 and Center Road, and from two lanes to four lanes between Center Road and I-75. Work will include drainage and safety improvements. Shared use paths, raised medians, wildlife crossings, signing and pavement markings, lighting, signalization, and Intelligent Transportation System (ITS) features will also be part of the project.

Construction began in February 2022. Design is anticipated to finish in summer of 2022 on this design-build project.

Project Updates

May 31, 2022
SR 777 River Road from US 41 to I-75: Construction project: Motorists can expect tree cutting along the southbound roadway from Tempest Harbor Loop to Center Rd; excavation of the pond area south of Venice Avenue along northbound River Road as well as clearing, embankment and drainage activities on both sides of the road between Venice Avenue and Center Road and on Venice Avenue, west of River Road. FPL will continue relocation of their overhead power lines from south of Center Road to south of Venice Avenue on the east side of the road. Overall completion expected in winter 2024.

May 25, 2022
SR 777 River Road from US 41 to I-75: Construction project: Motorists can expect to see excavation of the pond area south of Venice Avenue on the east side of River Road as well as clearing, embankment and drainage activities on both sides of road, between Venice Avenue and Center Rd. Embankment activities will start on Venice Avenue, west of River Road. FPL will continue relocation of their overhead power distribution lines from south of Center Road to south of Venice Avenue on the east side of the road. Overall completion expected in winter 2024.

May 16, 2022
SR 777 River Road from US 41 to I-75: Construction project: Motorists will see continued excavation of the pond area and embankment activities south of Venice Avenue on the east side of River Road and on Venice Ave, west of River Road. Clearing of trees is taking place on both sides of River Rd from I-75 to US 41. FPL will be on site to relocate their overhead power line from south of Center Road to south of Venice Avenue on the east side of the road. Overall completion of the project is expected in winter 2024.

Project Schedule

PD&E Study and Roadway Design: Mid-2021 to Early 2022
Public Meeting: Early 2022
Construction: Early 2022 to Early 2025

Public Involvement

The Florida Department of Transportation District One held a public meeting on January 27, 2022 to share information about a design-build project to widen River Road (State Road (SR) 777) from north of US 41 to south of I-75 in Sarasota County.

View Factsheet
Contact Information
Communications Team
Mary Brooks
941-800-2150
RiverRdInfo@QCAusa.com
Communications Team
Communications Office
fdot-d1comm@dot.state.fl.us
Media Inquiries
Andy Orrell
863-519-2828
Andy.Orrell@dot.state.fl.us
Project Documents
Project Images