SR 29 from North of New Market Road North to SR 82

District Office
L.K. Nandam, P.E.
District One Secretary

801 N. Broadway Ave.
Bartow, Florida 33830

Tel: 800-292-3368
Fax: 863-534-7265
E-Mail Us

Additional Contacts
Staff Directory

Welcome

The Florida Department of Transportation (FDOT), District One, is designing improvements to SR 29 in Collier County. The entire corridor limits extend approximately 16 miles along SR 29 from Oil Well Road to south of SR 82. The corridor has been divided into five segments which will accelerate the design process. The proposed roadway improvement consists of increasing capacity on SR 29 by widening the existing two-lane undivided segment of SR 29 to four lanes, as well as providing a bypass around downtown Immokalee.

This project begins at New Market Road and ends at SR 82. On the south end it will connect to the new Immokalee bypass and on the north end it will connect to the SR 82 roundabout. The final roadway will consist of two 12-foot travel lanes in each direction with 4-foot paved inside shoulders, 10-foot (5-foot paved) outside shoulders, and a 30-foot grass median.

There will be a public meeting during the design phase. Meetings will be held with elected and appointed public officials, other representatives of public agencies, and public/special interest groups to discuss the progress of the design.

Para revisar este sitio web en español, utilice el enlace en la barra lateral en el lado izquierdo de esta página.

Si ou ta renmen resevwa enfòmasyon sa-a an Kreyòl, tanpri kontakte Jimmy Vilce nan Depatman Transpotasyon Eta Florid, nan (863) 519-2311.

Please click the Documents and Publications tab to view documents about this project.

Project At-A-Glance



District
One (Southwest Florida)

FPID
417540-6

Estimated Construction Start Date
Late 2025

Cost
Estimated Construction Cost - $18.8 Million

Lengths and Limits
SR 29 from New Market Road/Westclox Road to SR 82, a distance of approximately 3 miles

Design Consultant
Faller, Davis and Associates, Inc.

Consultant Project Manager
Logan Barile, P.E.

FDOT Project Manager
Chris Speese
Tel: (239)225-1973
christopher.speese@dot.state.fl.us



 'project title' location map

Click here for full screen map.