Sunday, May 12 through Saturday, May 19, 2024
This week, crews will be installing signs along US17, SR 540, and 1st Street South.
- Northbound 1st Street South at the intersection with SR 540 has been reduced to one lane and will remain that way as this is a permanent alignment. A new permanent traffic separator has been constructed in the location of the old northbound inside lane.
- Southbound 1st Street South will be reduced to one lane from 9 p.m. to 7:30 a.m., Sunday, May 12, through Thursday, May 16, 2024.
- SR 540 westbound approaching US 17 will be reduced to two lanes from 8 p.m. to 5 a.m., Sunday, May 12, through Thursday, May 16, 2024.
- SR 540 eastbound from US 17 to 1st Street will be reduced to one lane from 8 p.m. to 5 a.m., Sunday, May 12, through Thursday, May 16, 2024.
- US 17 northbound will be reduced to one lane at the intersection with SR 540 from 8 p.m. to 5 a.m., Sunday, May 12, through Thursday, May 16, 2024.
- US 17 southbound will be reduced to one lane at the intersection with SR 540 from 8 p.m. to 5 a.m., Sunday, May 12, through Thursday, May 16, 2024.
- Use caution, be prepared to merge and expect delays.