441524-1 US 41 (Tamiami Trail) from William Street to the Peace River Bridge
Roadwatch UpdateProject Details
| Work Type: | Safety Study |
|---|---|
| Phase: | Construction |
| Limits: | from William Street to Peace River Bridge in Downtown Punta Gorda |
| Length: | 0.9 miles |
| City: | |
| County: | |
| Road: | |
| Construction Cost: | $24.4 Million |
| Start of Current Phase: | Mid 2024 |
| Est. Completion of Current Phase: | Late 2026 |
About
Project Information
The intent of this project is to enhance safety for all users of the roadway (including motorists, pedestrians, and bicyclists) on this northbound, three-lane, one-way section of Tamiami Trail (US 41) and advance goals of walkability and strategic investment/development within Downtown Punta Gorda as set forth in the City of Punta Gorda’s Comprehensive Plan and Plan Punta Gorda – 2019 Citywide Master Plan.
The Florida Department of Transportation conducted extensive public outreach throughout the duration of the study to help determine the best options to consider in order to maximize the results and value of the Resurfacing, Restoration, and Rehabilitation project. Potential elements that were considered include (but are not limited to) strategies to maintain consistent travel time, minimize lane changing, discourage aggressive driving, enhance pedestrian and bicycle facilities along with connections to existing area pathways and trails.
This study combined multiple project phases, including Planning, Project Development and Environment (PD&E), and Design to accelerate the project schedule and maximize the value of the project.
Public Involvement
The Florida Department of Transportation (FDOT), District One, hosted a public meeting for the Northbound Tamiami Trail (US 41/SR 45) Complete Street Improvements (Financial Project No.: 441524-1-32-01). The project specifically includes roadway, pedestrian, and bicycle safety improvements along Northbound Tamiami Trail from William Street to Peace River Bridge in Downtown Punta Gorda, Charlotte County. The public meeting was held to present information and gather public input on the proposed design of the improvements.
There were two ways to participate in the public meeting: attend the in-person event or register for and join the live online (virtual) event.
In-Person Event: The in-person event was scheduled for Thursday, January 26, 2023, at the Charlotte Harbor Event and Conference Center, 75 Taylor St, Punta Gorda, FL 33950. The “open house” event took place from 5 p.m. to 7 p.m.
Live Online (Virtual) Event: The live online (virtual) event was scheduled for Tuesday, January 31, 2023, from 6 p.m. to 7 p.m. Please register to attend at bit.ly/TamiamiTrailPublicMeeting. The virtual event could also be accessed online through the project website at https://www.swflroads.com/project/441524-1. Once registered, attendees received a confirmation email containing information about joining the meeting online. Please note, Internet Explorer cannot be used to register or attend the live online (virtual) event.
All meeting materials are available online for viewing through the project website starting January 19, 2023. A copy of these materials was also displayed at the in-person and live online (virtual) events.
The same material was presented at both events. You may choose any combination of the provided options to review the materials and submit your comments.
FAQs
1. Paving (August - November)
Crews are working on placing the final asphalt layer across the corridor
Work is underway on U.S. 17 and will shift to U.S. 41 northbound (NB) next.
WHAT TO EXPECT:
Nighttime paving work
Lane closures in active work zone
- Slow- moving construction vehicles
2. Surface Prep and Rumble Strip Installation (Late August - Early September)
Crews will sweep, prepare the surface, and install rumble strips on U.S. 17
WHAT TO EXPECT:
Small, short-term nighttime lane closures
3. Final Striping, Lane Configuration, and Retta Esplanade Signal (September - October)
Permanent striping will be applied across the corridor, including the final NB U.S. 41 lane configuration.
Striping will occur in phases, and drivers will begin seeing updated lane guidance as the corridor transitions into its permanent layout.
Retta Esplanade Signal
The Retta Esplanade signal is currently being prepared for activation.
Because the signal heads are already installed for the final lane arrangement, activation is expected to align closely with the completion of final striping.
FDOT and the City will announce the activation date once confirmed.
WHAT TO EXPECT:
Nighttime striping operations
Lane shifts as new markings are installed
4. Traffic Monitoring Loops and Thermoplastic Markings (Mid-September - October)
After the new asphalt has cured, crews will install traffic sensors (used for signal timing and monitoring) and final long-lasting pavement markings.
Public Impact:
Occasional nighttime lane closures and brief work zones in finished paved areas
5. Corridor-Wide Signal Retiming (October - November)
Charlotte County - supported by FDOT - will adjust traffic-signal timing along U.S. 41 and U.S. 17 to make sure all signals and roundabout work smoothly together.
WHAT TO EXPECT:
Minor temporary flow changes during tuning
Improved consistency once timing is finalized
All activities are weather-dependent and subject to change based on paving progress, asphalt curing time, and contractor scheduling. Updates will be provided as the corridor advances toward final completion.
----
What do I need to know about roundabouts?
4005-Multi-lane-Roundabout-Handout.pdf
FDOT Safety: How to Use a Roundabout
FDOT Roundabouts 101: RIGHT OF WAY IN A ROUNDABOUT
FDOT Roundabouts 101: TRUCK NAVIGATION IN A ROUNDABOUT
Where will the roundabout be located?
The roundabout will be at the intersection of Tamiami Trail (US 41) and Carmalita Street.
Estimated Completion?
This estimated completion for this contract is Fall 2026
Contact Information
RoadWatch
-
U.S. 41 (Tamiami Trail) from William Street to Peace River Bridge: Construction project: The contractor is working to activate the new signals and lighting along U.S. 41 northbound.
U.S. 41 (Tamiami Trail) from William Street to Peace River Bridge: Construction project: The contractor is working to activate the new signals and lighting along U.S. 41 northbound. Final asphalt paving is expected to begin, changing the configuration of U.S. 41 northbound from three lanes to two lanes with dedicated turn lanes.
- Expect potential lane closures for crews to work on signalization and lighting.
- Expect potential overnight road closures as crews pave the roadway and restripe to the new road configuration.
- Detours will be instituted to guide motorists around the closed sections of roadway. The right turn lane at Taylor Street to U.S. 41 northbound will be closed to allow motorists to adjust to the new configuration.
Motorists should use caution and expect to see trucks moving throughout the project.
The above activities are subject to change based on weather and unforeseen conditions. Expected completion in fall 2026