Project Details
Work Type: Sidewalk
Phase: Construction
Limits: from Shoreland Boulevard to Old Olga Road/Buckingham Road
Length: 4.5 miles
County:
Road:
Construction Cost: $4.1 million
Start of Current Phase: Mid 2021
Est. Completion of Current Phase: Late 2022
About

Project Description

The Florida Department of Transportation’s (FDOT) contractor, V&H Construction, began work in August, 2021 to add a 10-foot-wide asphalt shared use path on the northside of SR 80 (Palm Beach Boulevard) from Shoreland Drive to Old Olga Road/ Buckingham Road. An eight-foot-wide sidewalk will be constructed on the southside of SR 80 from Orange River Boulevard to Verandah Boulevard, from Parker Avenue to Upcohall Avenue and Weber Boulevard to Loring Way, tying existing sidewalk together. The construction team is coordinating with emergency and municipal services. During construction, the contractor will maintain public services such as mail delivery, garbage/recycle and bus services. Police/Fire and Emergency Medical Services (EMS) will be notified of construction activities.

Project Improvements

  • 10-foot-wide asphalt shared use path
  • 8-foot-wide sidewalk
  • Bus shelter pads
  • Curb and gutter
  • Drainage improvements
  • Lightning
  • Signal work

 

View Factsheet
Contact Information
Design Project Manager
Luella Pierce
(239) 985-7868
Communications Team
Lisa Macias
239-985-7800
For Media Inquiries Only
d1-pio@dot.state.fl.us
Project Documents
Project Images
Typical Section