View project: SR 777 River Road from US 41 to I-75
-
S.R. 777 River Road from I-75 to U.S. 41: Construction project: Road embankment installation continues on the northbound roadway from Aucilla Drive to U.S. 41, and Venice Avenue to I-75. As embankment is completed, drainage installations, subgrade mixing, curb placement, and roadway grading will continue. Sod installation, signal, ITS, and lighting work are ongoing. Trucks will be crossing the road at various locations using intermittent flagging operations. Pothole maintenance will continue as necessary on all current travel ways through the project. Crews will continue mainline asphalt paving operations from Myakka Trails to U.S. 41 intermittently throughout the week. Flagging operations may be used from Myakka Trails to U.S 41 to guide travelers through the work area as paving occurs. Please use caution and follow all road work and regulatory signs when traveling through the project.