SR 777 River Road from I-75 to US 41: Construction project: Road embankment installation continues on the northbound roadway from Aucilla Drive to US 41. As embankment is completed, drainage installations, subgrade mixing, curb placement, and roadway grading will continue. Sod installation, signal, ITS, and lighting work is ongoing. Trucks will be crossing the road at various locations using intermittent flagging operations. Pothole maintenance will continue as necessary on all current travel ways through the project.
- Traffic on SR 777 (River Road) has switched to the new southbound alignment, from just south of Aucilla Drive to just north of US 41. All motorists will use the future southbound River Road lanes from Venice Avenue to just north of US 41. Please watch for signs directing traffic and use caution when exiting neighborhoods onto River Road. Motorists are encouraged to slow down while traveling through the work zone. The new work zone created by the shift will become the future northbound alignment.