I-75 From South of Bonita Beach Road to North of Alico: Construction Project: Nighttime Lane closure operations will Continue Sunday Nights through Thursday Nights for resurfacing operations for the next few months.
Paving operations are scheduled to resume Monday night, April 21, 2025, due to the holiday weekend.
Daytime activities will include installation of sign bases and conduit installation for I.T.S. items.
New guardrail installation in the medians and overpasses. This work will be performed during the daytime from inside the right-of-way away from the travel lanes or behind shoulder closures as needed.
The current work schedule is subject to change due to weather or other unforeseen circumstances.