-
S.R. 777 River Road from I-75 to U.S. 41: Construction project: Road embankment installation continues on the northbound roadway from Aucilla Drive to U.S. 41, and Venice Avenue to I-75. As embankment is completed, drainage installations, subgrade mixing, curb placement, and roadway grading will continue. Sod installation, signal, ITS, and lighting work are ongoing. Trucks will be crossing the road at various locations using intermittent flagging operations. Pothole maintenance will continue as necessary on all current travel ways through the project. Third lane widening operations on the southbound lanes will begin at Venice Avenue. Flagging operations may be used from Venice Avenue to Center Road to guide travelers through the work area.
-
U.S. 41 (S.R. 45) from North of U.S. 19 (S.R. 55) to 69th Street East (Erie Road). Construction project: The Florida Department of Transportation (FDOT) will construct median modifications to reduce conflict points and improve safety starting in early 2026. The project improvements include drainage, guardrail, milling and resurfacing on U.S. 41 from north of S.R. 55 (U.S. 19) to north of 69th Street East (Erie Road). Crews will apply new signing and pavement markings once the final paving has been completed. The project limits are approximately 2.6 miles.
Ramp closures (weather permitting):
Sunday, March 15: The U.S. 41 northbound to U.S. 41 southbound ramp will be closed from 8 p.m. to 6 a.m. Motorists will be detoured to continue northbound, turning left onto Experimental Farm Road, then motorists can turn left onto southbound U.S. 19 to continue to southbound U.S. 41.
Monday, March 16: The U.S. 41 southbound ramp to northbound U.S. 19 will be closed from 8 p.m. to 6 a.m. Motorists will be detoured to continue southbound past the ramp via the loop, following the loop to head back northbound, passing south of the ramp onto U.S. 19 northbound.
Please use caution and follow posted signage during the ramp closures and detours.
- Motorists can expect intermittent interior and exterior lane closures northbound and southbound on U.S. 41 as crews continue concrete, drainage, guardrail and sod work in the median within the project limits during the day.
- Throughout the next few months, weather permitting, motorists can expect intermittent interior and exterior nighttime lane closures on northbound and southbound U.S. 41 as crews continue milling and resurfacing operations.
- Please be aware of workers and construction equipment /noise during daytime and overnight hours.
- Motorists can expect temporary uneven pavement throughout the project limits until final completion.
- Plan for additional time or choose an alternate route if needed.
- Estimated completion is mid-2026.