-
S.R. 70 from Lorraine Road to Bourneside Boulevard: Construction project: This project includes widening S.R. 70 from Lorraine Road to Bourneside Boulevard from a two-lane undivided roadway to a four-lane or six-lane divided roadway, depending on the location, construction of roundabouts on S.R. 70 at Uihlein Road, Del Webb Boulevard, and Bourneside Boulevard, intersection improvements at the existing signalized intersection of Greenbrook Boulevard and Lorraine Road, construction of four bridges over two Braden River crossing locations, new drainage system, construction of 10-foot shared use paths, street lighting, and landscaping, and installation of new fiber optic cable connecting the two signalized intersections to Manatee County’s regional Advanced Traffic Management System (ATMS).
Safety Notice - Recently, bicyclists and pedestrians have been observed entering the work zone and using shared-use paths within the project limits. Although these areas may appear finished, construction activities are still ongoing. These areas are not open to the public and may contain open excavations, fresh asphalt, or uncured concrete, posing significant safety hazards to anyone not affiliated with the project. These roadways and shared-use paths within the work zone are clearly marked as closed with signage. Additionally, vehicles have been observed driving through closed side streets while workers are present, creating a serious risk of injury or accident.
This week’s work will consist of:
· Excavation of the pond on the north side of S.R. 70, west of Uihlein Road.
· Installing slope protection rip-rap on both S.R. 70 westbound bridges. Forming and pouring concrete pile caps.
· Demolition of the existing S.R. 70 median east of Lorraine Road. Flagging and lane closures will be present in both directions of S.R. 70 for this work. Please exercise caution with construction equipment and personnel working close to current S.R. 70 traffic.
· Grading base between Bourneside Boulevard and Polo Run on the north side of S.R. 70 for shared use path.
· Installing signalization hardware at the intersection of Greenbrook Boulevard and S.R. 70.
· Installing light conduit and foundations on the north side of S.R.70 between Uihlein Road and Bourneside Boulevard.
Greenbrook Boulevard is closed until May 2026 to allow for the construction of the south portion of the Greenbrook Boulevard intersection. During this time, no traffic is permitted on Greenbrook Boulevard between S.R. 70 and Skip Jack Loop in either direction. The north side of Greenbrook Boulevard and S.R. 70 will remain open. A full detour route and message boards are in place in advance of the closure.
Please use caution and watch for trucks and construction vehicles entering or exiting the work zone throughout the construction limits. Work will take place Monday through Saturday, from 7 a.m. to 5 p.m. Be aware of workers and flaggers in the area.
The estimated completion date for construction is Summer 2027.
-
S.R. 70 from Lorraine Road to Bourneside Boulevard: Construction project: This project includes widening S.R. 70 from Lorraine Road to Bourneside Boulevard from a two-lane undivided roadway to a four-lane or six-lane divided roadway, depending on the location, construction of roundabouts on S.R. 70 at Uihlein Road, Del Webb Boulevard, and Bourneside Boulevard, intersection improvements at the existing signalized intersection of Greenbrook Boulevard and Lorraine Road, construction of four bridges over two Braden River crossing locations, new drainage system, construction of 10-foot shared use paths, street lighting, and landscaping, and installation of new fiber optic cable connecting the two signalized intersections to Manatee County’s regional Advanced Traffic Management System (ATMS).
Safety Notice - Recently, bicyclists and pedestrians have been observed entering the work zone and using shared-use paths within the project limits. Although these areas may appear finished, construction activities are still ongoing. These areas are not open to the public and may contain open excavations, fresh asphalt, or uncured concrete, posing significant safety hazards to anyone not affiliated with the project. These roadways and shared-use paths within the work zone are clearly marked as closed with signage. Additionally, vehicles have been observed driving through closed side streets while workers are present, creating a serious risk of injury or accident.
This week’s work will consist of:
- Excavation of the pond on the north side of S.R. 70, west of Uihlein Road.
- Installing slope protection rip-rap on both S.R. 70 westbound bridges. Forming and pouring concrete pile caps.
- Demolition of the existing S.R. 70 median east of Lorraine Road. Flagging and lane closures will be present in both directions of S.R. 70 for this work. Please exercise caution with construction equipment and personnel working close to current S.R. 70 traffic.
- Grading base between Bourneside Boulevard and Polo Run on the north side of S.R. 70 for shared use path.
- Installing signalization hardware at the intersection of Greenbrook Boulevard and S.R. 70.
- Grading roadway stabilization and curb pad on Greenbrook Boulevard south of S.R. 70. Installing drainage inlet tops on Greenbrook Boulevard.
- Installing light conduit and foundations on the north side of S.R.70 between Uihlein Road and Bourneside Boulevard.
Greenbrook Boulevard is closed until May 2026 to allow for the construction of the south portion of the Greenbrook Boulevard intersection. During this time, no traffic is permitted on Greenbrook Boulevard between S.R. 70 and Skip Jack Loop in either direction. The north side of Greenbrook Boulevard and S.R. 70 will remain open. A full detour route and message boards are in place in advance of the closure.
Please use caution and watch for trucks and construction vehicles entering or exiting the work zone throughout the construction limits. Work will take place Monday through Saturday, from 7 a.m. to 5 p.m. Be aware of workers and flaggers in the area.
The estimated completion date for construction is Summer 2027.
-
S.R. 70 from Bourneside Boulevard to Waterbury Road, Bradenton: Construction project: This project includes widening S.R. 70 from Bourneside Boulevard to Waterbury Road from a two-lane undivided roadway to a four-lane divided roadway, Safety features will include roundabouts to be constructed at 197th Street East/Lindrick Lane, 213th Street East, 225th Street East/Panther Ridge Trail and County Road 675/Waterbury Road. The project will also include the installation of a new drainage system, new curb and gutter, construction of 10-foot shared-use paths and five-foot paved shoulders on both sides of the roadway, street lighting throughout the project and landscaping inside the roundabouts.
Notice: Please refrain from entering the work zone. New pavement has recently been installed that gives the impression of completed areas of work, but these areas are still active and use by non-project staff is a safety hazard as trucks, equipment, and work is ongoing. All new shared use paths and roadways remain closed until further notice. The work zone is an active construction area. For the safety of all, please stay out of the work area.
This week’s work will consist of:
· Swale grading west of Lindrick Lane.
· Grading and compacting base material for the shared use path on the north side of S.R. 70 at 197th Street.
· Grading for temporary asphalt at Panther Ridge Trail and 213th Street.
· Grading and sodding the swale on the south side of S.R. 70 east of Meadow Dove Lane.
· Relocating utilities and installing new electrical transformers on the north side of S.R. 70. Pulling lighting conductor to energize installed lighting.
213th Street and Panther Ridge Trail are closed to grade for temporary roadway for future traffic control phasing. During the closures, no traffic will be permitted to enter or exit 213th Street and Panther Ridge Trail via S.R. 70. A full detour is in place, with message boards directing traffic along the detour route. The closure is expected to remain in effect until April 10th.
The estimated completion date for construction is Summer 2027.
-
S.R. 70 from Bourneside Boulevard to Waterbury Road, Bradenton: Construction project: This project includes widening S.R. 70 from Bourneside Boulevard to Waterbury Road from a two-lane undivided roadway to a four-lane divided roadway, Safety features will include roundabouts to be constructed at 197th Street East/Lindrick Lane, 213th Street East, 225th Street East/Panther Ridge Trail and County Road 675/Waterbury Road. The project will also include the installation of a new drainage system, new curb and gutter, construction of 10-foot shared-use paths and five-foot paved shoulders on both sides of the roadway, street lighting throughout the project and landscaping inside the roundabouts.
Notice: Please refrain from entering the work zone. New pavement has recently been installed that gives the impression of completed areas of work, but these areas are still active and use by non-project staff is a safety hazard as trucks, equipment, and work is ongoing. All new shared use paths and roadways remain closed until further notice. The work zone is an active construction area. For the safety of all, please stay out of the work area.
This week’s work will consist of:
· Grading stabilization and base west of Lindrick Lane for future eastbound lanes.
· Grading and compacting base material for the shared use path on the north side of S.R. 70 at 197th Street.
· Grading for temporary asphalt at Panther Ridge Trail and 213th Street.
· Grading and sodding the swale on the south side of S.R. 70 east of Meadow Dove Lane.
· Relocating utilities and installing new electrical transformers on the north side of S.R. 70. Pulling lighting conductor to energize installed lighting.
Meadow Dove Lane is closed for the construction of the south portion of the Meadow Dove Lane/C.R. 675 roundabout. During the closure, no traffic will be permitted to enter or exit Meadow Dove Lane via S.R. 70. A full detour is in place, with message boards directing traffic along the detour route. The closure is expected to remain in effect until the end of March 2026.
The estimated completion date for construction is Summer 2027.