Project Details
Work Type: Milling and Resurfacing
Phase: Construction
Length: 13.6 miles
City:
County:
Road:
Construction Cost: $22.9 million
Start of Current Phase: Mid 2024
About

The improvements on this project include milling and resurfacing the existing lanes along I-75 from South of Bonita Beach Road to North of Alico Road

FAQs

What time will the construction work occur on this project?

Work can be expected Sunday nights through Thursday nights 8:00 p.m. to 6:00 a.m. 

*Weather or other unexpected conditions permitting

View Factsheet
Contact Information
Communications Team
Bryn Parsons
239-985-7864
Bryn.Parsons@dot.state.fl.us
For Media Inquiries Only
fdot-d1comm@dot.state.fl.us
RoadWatch
  • SR 93 (I-75) From South of Bonita Beach Rd to North of Alico:  Milling and resurfacing of existing lanes.

    Nighttime milling and resurfacing operations are scheduled over the next several months, Sunday nights through Thursday nights 8:00 p.m. to 6:00 a.m.

    • Daytime activities will include installation of sign bases and conduit installation for ITS items.
    • Storm Sewer installations will start within the Right-of-Way, West of the Southbound On-ramp for I-75. This work will be performed during the daytime from inside the Right of Way away from the travel lanes or behind shoulder closures as needed.
Project Images
Open trench work
Crews are installing a Wrong-Way Detection sign base
Crews are installing slip base at the Northbound Alico Off-Ramp
I-75 southbound