446344-1 SR 93 (I-75) From South of Bonita Beach Road to North of Alico Road
Roadwatch UpdateProject Details
| Work Type: | Milling and Resurfacing |
|---|---|
| Phase: | Construction |
| Length: | 13.6 miles |
| City: | |
| County: | |
| Road: | |
| Construction Cost: | $22.9 million |
| Start of Current Phase: | Mid 2024 |
About
The improvements on this project include milling and resurfacing the existing lanes along I-75 from South of Bonita Beach Road to North of Alico Road
View Factsheet
Contact Information
| Communications Team |
|---|
|
Bryn Parsons
239-985-7864
Bryn.Parsons@dot.state.fl.us
|
| For Media Inquiries Only |
|
fdot-d1comm@dot.state.fl.us
|
RoadWatch
-
I-75 From South of Bonita Beach Road to North of Alico: Construction Project: Nighttime Lane closure operations will continue Sunday Nights through Thursday Nights for resurfacing operations for I-75 northbound and southbound.
- Paving Operations have resumed and will continue in the southbound and northbound lanes of I-75 over the next three months. All paving work is subject to change due to weather conditions and low temperature restrictions.
- Daytime activities will include:
- Continued installation of signs and I.T.S. items.
- Shoulder treatment and sod placement at various locations from Alico Road to the Lee/Collier County line.
- The current work schedule is subject to change due to weather or other unforeseen circumstances.