Project Details
Work Type: Resurfacing
Phase: Construction
Length: 1.6 miles
City:
County:
Road:
Construction Cost: $3.6 million
Start of Current Phase: Late 2022
Est. Completion of Current Phase: Late 2023
About

The improvements under this contract consist of milling and resurfacing, shoulder/turn lane widening, sidewalk replacement, drainage improvements, signing and pavement markings, with signal and lighting improvements for approximately 1.6 miles along SR 758 (Midnight Pass Rd.) from SR 72 (Stickney Point Rd.) to Shadow Lawn in Sarasota County, Florida.

FAQs
  • Construction starts December 2022
  • Expected completion is fall 2023
  • Temporary lane closures are expected
  • Expect noise from back-up alarms, trucks, and construction equipment.
  • Estimated cost: $3.6 million

 

View Factsheet
Contact Information
Communications Team
Adam Rose
863-519-2774
adam.rose@dot.state.fl.us
Communications Team
Barbara Catlin
941-302-5048
barbara.catlin@dot.state.fl.us
For Media Inquiries Only
fdot-d1comm@dot.state.fl.us
RoadWatch
    • Two lanes will remain open during construction as will access to businesses and residences.
    • Milling and resurfacing will begin after Easter, the traditional end of “season,” and will be done overnight. Anticipated start date for this is approximately mid to late April.
    • Construction “maintenance of traffic” devices will be removed each day.