Project Details
Work Type: Intersection Construction
Phase: Construction
City:
County:
Road:
Construction Cost: $10 million
Start of Current Phase: Late 2024
Est. Completion of Current Phase: Mid 2026
About

U.S. 27 (S.R. 25) FROM S OF TOWER ST TO N OF TOWER ST - Rigid Pavement (Concrete)
INTERSECTION Reconstruction (Project length - 0.300 miles) Goes with 
 U.S. 27 (S.R. 25) FROM SHORELINE DR TO DAVIS & GAINES RD - Milling and resurfacing, sidewalk,
widening, drainage improvements, signalization, guardrail, signing and pavement marking, lighting, and landscaping. Project length - 6.443 miles

Public Involvement

Aika Ranieri

Community Outreach 

Florida Department of Transportation

Heartland Operations Center

PH: 863-471-4881 

Ai.Ranieri@dot.state.fl.us

Or

Nancy Morgan

Community Outreach

Florida Department of Transportation

Heartland Operations Center

Cell or Text: 941-720-6335

nancy.morgan@dot.state.fl.us

View Factsheet
Contact Information
Communications Team
Nancy Morgan
941-720-6335
Nancy.morgan@dot.state.fl.us
Communications Team
Aika Ranieri
(863) 464-0743
ai.ranieri@dot.state.fl.us
For Media Inquiries Only
fdot-d1comm@dot.state.fl.us
RoadWatch
  • S.R. 25 (U.S. 27) from Shoreline Drive to Davis and Gaines Road and S.R. 25 (U.S. 27) from North of Tower Street to South of Tower Street: Construction project: Crews are reconstructing rigid pavement on S.R. 25 (U.S. 27) from north of Tower Street to south of Tower Street. Additionally, milling and resurfacing work is ongoing on U.S. 27 from Shoreline Drive to Davis and Gaines Road.

    • Daily lane closures continue on S.R. 25 (U.S. 27) northbound and southbound for shoulder widening sitewide.
    • Use caution at the S.R. 25 (U.S. 27) & Dal Hall Boulevard/Tower Street Intersection for construction traffic entering / leaving the median work zone.
    • The S.R. 25 (U.S. 27) and Dal Hall Boulevard/Tower Street intersection will have a median closure from March 13 – 23. Please follow detour routes for eastbound or westbound movements.
    • Motorists should use caution in the area and watch for workers and equipment in the construction zone.
    • Anticipated completion is late 2026.
Project Documents
Archived Project Documents (These documents have been archived for reference and research purposes.)
Project Images
Overview of the Tower Street detour route, showing the intersection closure at U.S. 27, Dal Hall Boulevard, and Tower Street and the alternate route using County Road 621, Plaza Avenue, and Lake Clay Drive.
Overview of the Dal Hall Boulevard detour route, showing how traffic will be redirected around the closed intersection via U.S. 27, East Interlake Boulevard, County Road 621, and Main Avenue.
Close-up view of the intersection closure at U.S. 27 and Dal Hall Boulevard/Tower Street, highlighting the work zone and detour traffic flow directions
Signalized intersection with multiple lane closures delineated by traffic barrels.