444313-1 SR 17 (Scenic Highway) from 5th Avenue to North Crooked Lake Drive
Project Details
Work Type: | Milling and Resurfacing |
---|---|
Phase: | Completed |
Limits: | 5th Avenue to North Crooked Lake Drive in Babson Park, Florida |
City: | |
County: | |
Road: | |
Construction Cost: | $2.6 million |
Completion Date: | 09/24/2025 |
About
The Florida Department of Transportation completed a Full Depth Reclamation (FDR) Project on SR 17 (Scenic Highway) from 5th Street to North Crooked Lake Drive in September 2025.
Full Depth Reclamation (FDR) is the process of recycling or reclaiming the old roadway and underlying base and using them to create a stronger base for the new roadway. As the reclaimer grinds the old roadway asphalt and base together, a mix of Portland cement and emulsifiers are added to form a new stronger roadway base. This is all done in place, followed by a roller to compact the material and a grader to grade it to the desired level and slope, before a prime coat and new asphalt layer is paved on top.
The benefits of this process include a stronger, more uniform and moisture resistant base, recycling of the existing materials, saving money, time and natural resources, removal of deep cracking within the existing pavement structure, and less impact to traffic when compared to full reconstruction of the roadway.
In addition to the new roadway, project improvements included drainage improvements, shoulder widening, reconstruction of side street entrances and some driveway aprons.
Contact Information
Communications Team |
---|
Sandra Mancil
863-519-4116
Sandra.Mancil@dot.state.fl.us
|
For Media Inquiries Only |
fdot-d1comm@dot.state.fl.us
|