446207-1 S.R. 25 (U.S. 27) from Shoreline Drive to Davis & Gaines Road
Roadwatch UpdateProject Details
| Work Type: | Milling and Resurfacing |
|---|---|
| Phase: | Construction |
| Limits: | from Shoreline Drive to Davis & Gaines Road |
| Length: | 6.443 miles |
| City: | |
| County: | |
| Road: | |
| Construction Cost: | $17,162,200 |
| Start of Current Phase: | Mid 2021 |
About
The Florida Department of Transportation (FDOT), District One, welcomes you to the Public Meeting
for the State Road (S.R.) 25 (U.S. 27) from Shoreline Drive to Davis & Gaines Road project. FDOT is
hosting this Public Meeting to provide you with the opportunity to express your views about the
proposed improvements. Scan the QR code to visit the project website for additional details.
The objective of the project is to extend the service life of the existing pavement and improve safety on S.R. 25 (U.S. 27) from
Shoreline Drive to Davis & Gaines Road. The improvements include:
• Milling and resurfacing the existing pavement. Inside paved shoulders will be
added in the medians.
• A separate design project for the Tower Street intersection will be constructed
with this project. The intersection will be fully reconstructed with concrete
pavement.
• Bicycle keyhole lanes will be constructed at the right turn lanes.
• Proposed sidewalk improvements to increase pedestrian connectivity.
• Proposed guardrail and traffic signal replacement to meet current standards.
• Modify median openings to improve safety and meet current requirements.
Three full median openings will be converted to directional openings and two
openings will be closed.
o Proposed directional median openings at C.R. 29, S. Main Ave., and
Heartland Blvd.
o Proposed median closures at Old SR 8, and South of Lake McCoy (no
side street).
Public Involvement
Aika Ranieri
Community Outreach Specialist
Florida Department of Transportation
Heartland Operations Center
PH: 863-471-4881 / 863-464-0743
Ai.Ranieri@dot.state.fl.us
OR
Nancy Morgan
Community Outreach
nancy.morgan@dot.state.fl.us
941.720.6335
Contact Information
RoadWatch
-
S.R. 25 (U.S. 27) from Shoreline Drive to Davis and Gaines Road and from North of Tower Street to South of Tower Street: Construction project: Crews are reconstructing rigid pavement on S.R. 25 (U.S. 27) from north of Tower Street to south of Tower Street. Additionally, milling and resurfacing work is ongoing on U.S. 27 from Shoreline Drive to Davis and Gaines Road.
- Daily daytime and nighttime lane closures continue on northbound and southbound S.R. 25 (U.S. 27) for paving, lighting, signalization, signage, curb, sidewalk, and other roadway activities throughout the project limits.
- Nighttime curb, gutter, sidewalk, crosswalk, and drainage-flume work is scheduled through mid-October.
- Nighttime paving activities are scheduled to continue through mid-October. Daytime paving may also occur in various locations.
- Intermittent lane closures may occur at the U.S. 27 and Dal Hall Boulevard/Tower Street intersection while crews complete roadway work. Motorists should use extra caution in this area.
- Daytime lighting, signalization, and signage activities will continue throughout the project limits.
- Motorists should use caution at the U.S. 27 and Dal Hall Boulevard/Tower Street intersection due to construction traffic entering and leaving the work zone.
- The northbound U.S. 27 lane shift moving traffic onto the newly constructed concrete pavement at the U.S. 27 and Dal Hall Boulevard/Tower Street intersection has been completed. Drivers should use extra caution while traveling through this area.
- Motorists should remain alert for daytime and nighttime lane closures, workers, equipment, and changing traffic patterns throughout the construction zone.
Anticipated completion is late 2026.