Project Details
Work Type: Milling and Resurfacing
Phase: Construction
Limits: SR 66 from US 17 (SR 35) to Charlie Creek
Length: 7.81 miles
City:
County:
Construction Cost: $9 million
About

Project Description: The improvements under this contract consist of reconstruction, resurfacing,
addition of Type F curb and gutter, sidewalk, updated pedestrian features, superelevation
correction, guardrail replacement, new drainage pipe and structures, updated signing, and
pavement markings of SR66 from SR35 (US17) to Charlie Creek.

Public Involvement

Aika Ranieri

Community Outreach Specialist

Florida Department of Transportation

Heartland Operations Center

PH: 863-471-4881 / 863-464-0743

Ai.Ranieri@dot.state.fl.us

OR

Nancy Morgan

Interim Community Outreach Manager

Heartland Operations

941.720.6335

nancy.morgan@dot.state.fl.us

FAQs

Project Improvements:

  • Milling and resurfacing
  • Adding Type F curb and gutter
  • Updated sidewalks and pedestrian features
  • Superelevation correction
  • Guardrail replacement
  • New drainage pipes and structures
  • Updated signage and pavement markings

 

View Factsheet
Contact Information
Communications Team
Nancy Morgan
941-720-6335
Nancy.morgan@dot.state.fl.us
Communications Team
Aika Ranieri
(863) 464-0743
ai.ranieri@dot.state.fl.us
For Media Inquiries Only
fdot-d1comm@dot.state.fl.us
RoadWatch
  • S.R. 66 from U.S. 17 (S.R. 35) to Charlie Creek: Construction project: Crews have completed major reconstruction activities along S.R. 66 from U.S. 17 to Charlie Creek. The project included milling and resurfacing, sidewalk construction, drainage improvements, guardrail installation, curb and gutter work, new pavement markings, and other safety enhancements.

    • The detour has now been lifted, and the newly reconstructed roadway is open to traffic in both directions
    • Eastbound and westbound lane closures and flagging operations will take place from Magnolia Street to Acorn Road beginning November 17, through November 21, 2025, between 7 a.m. and 5 p.m.
    • Motorists should anticipate longer delays in queues, follow posted signs, follow the speed limit, and consider alternative routes.
    • Estimated project completion is early 2026.