446229-1 SR 66 from US 17 (SR 35) to Charlie Creek
Roadwatch UpdateProject Details
| Work Type: | Milling and Resurfacing |
|---|---|
| Phase: | Construction |
| Limits: | SR 66 from US 17 (SR 35) to Charlie Creek |
| Length: | 7.81 miles |
| City: | |
| County: | |
| Construction Cost: | $9 million |
About
Project Description: The improvements under this contract consist of reconstruction, resurfacing,
addition of Type F curb and gutter, sidewalk, updated pedestrian features, superelevation
correction, guardrail replacement, new drainage pipe and structures, updated signing, and
pavement markings of SR66 from SR35 (US17) to Charlie Creek.
Public Involvement
Aika Ranieri
Community Outreach Specialist
Florida Department of Transportation
Heartland Operations Center
PH: 863-471-4881 / 863-464-0743
Ai.Ranieri@dot.state.fl.us
OR
Nancy Morgan
Interim Community Outreach Manager
Heartland Operations
941.720.6335
nancy.morgan@dot.state.fl.us
FAQs
Project Improvements:
- Milling and resurfacing
- Adding Type F curb and gutter
- Updated sidewalks and pedestrian features
- Superelevation correction
- Guardrail replacement
- New drainage pipes and structures
- Updated signage and pavement markings
Contact Information
| Communications Team |
|---|
|
Nancy Morgan
941-720-6335
Nancy.morgan@dot.state.fl.us
|
| Communications Team |
|
Aika Ranieri
(863) 464-0743
ai.ranieri@dot.state.fl.us
|
| For Media Inquiries Only |
|
fdot-d1comm@dot.state.fl.us
|
RoadWatch
-
S.R. 66 from U.S. 17 (S.R. 35) to Charlie Creek: Construction project: Crews have completed major reconstruction activities along S.R. 66 from U.S. 17 to Charlie Creek. The project included milling and resurfacing, sidewalk construction, drainage improvements, guardrail installation, curb and gutter work, new pavement markings, and other safety enhancements.
- The detour has now been lifted, and the newly reconstructed roadway is open to traffic in both directions
- Eastbound and westbound lane closures and flagging operations will take place from Magnolia Street to Acorn Road beginning November 17, through November 21, 2025, between 7 a.m. and 5 p.m.
- Motorists should anticipate longer delays in queues, follow posted signs, follow the speed limit, and consider alternative routes.
- Estimated project completion is early 2026.