Project Details
Work Type: Sidewalk
Phase: Construction
Limits: Hornet Drive, South 20th Street, Carol Avenue and East Hinson Avenue in Haines City
City:
County:
Construction Cost: $575,000
Start of Current Phase: Mid 2025
Est. Completion of Current Phase: Late 2025
About

The Florida Department of Transportation (FDOT) will build four new sidewalk sections in Haines City to enhance pedestrian connectivity. These new segments will link to existing sidewalks, improving safety and accessibility for students walking to school from nearby neighborhoods.

Project Improvements Include: 

  • Adding sidewalk along Hornet Drive, East Grace Avenue/Hornet Drive, South 20th Street and East Hinson Avenue
  • Improving accessibility at curb ramps that do not currently meet ADA requirements
  • Improving drainage and reconstructing sections of sidewalk that are broken or damaged
  • Milling, resurfacing and adding crosswalks in the following locations:
    • across South 20th Street at East Hinson Avenue and at Grace Avenue
    • across Carol Avenue and Norma Avenue at South 20th Street
    • across South 21st Street and South 22nd Street at Carol Avenue
  • Replacing driveway aprons that do not meet ADA requirements
  • Replacing fence on the north side of Hornet Drive

The majority of the work is scheduled during the summer when school is out. Lane closures required once school is back in session will be done between 9:30 a.m. and 1:30 p.m. or after 4:30 p.m.

View Factsheet
Contact Information
Communications Team
Sandra Mancil
863-519-4116
Sandra.Mancil@dot.state.fl.us
For Media Inquiries Only
fdot-d1comm@dot.state.fl.us
RoadWatch
  • Week of Sunday, June 8 through Saturday, June 14:

    Crews will begin working on drainage on Hornet Drive. Work will occur off the roadway with no planned lane closures. Use caution and watch for workers close to the road.

Project Documents
Project Images
Sidewalks being added during this project are shown in red. Existing sidewalks that they connect are shown in blue. New sidewalk will be constructed in four locations. One: on the east side of South 20th Street from East Grace Avenue to just north of Norma Avenue; Two: on the south side of Carol Avenue from South 2oth Street to South 22nd Street; Three: on the north side of Hornet Drive from South 30th Street to East Grace Avenue; and, Four: on the south of East Hinson Avenue from US 17/92 to Robinson Drive.