Project Details
Work Type: Resurfacing
Phase: Construction
Limits: Charlotte County Line to South of U.S. 41
Length: 8 miles
City:
County:
Road:
Construction Cost: $15.4 Million
Start of Current Phase: Mid 2026
Est. Completion of Current Phase: Mid 2027
About

The Florida Department of Transportation (FDOT) will begin milling and resurfacing State Road (S.R.) 776 from the Charlotte County line to south of U.S. 41. FDOT will also begin a median modification project on S.R. 776 from the Charlotte County line to Tangerine Woods Boulevard. While individual project schedules will vary, the combined contract begins in mid-2026 and spans just over 8 miles. Overall project cost is estimated at $15 million. FDOT will provide weekly RoadWatch updates via the project website.

Public Involvement

Sarasota Community Outreach Managers are available to assist with any questions you may have.

View Factsheet
Contact Information
Communications Team
Barbara Catlin
941-302-5048
barbara.catlin@dot.state.fl.us
Communications Team
Nancy Morgan
941-720-6335
Nancy.morgan@dot.state.fl.us
For Media Inquiries Only
RoadWatch
  • S.R. 776 from Charlotte County Line to South of U.S. 41: Construction project: The Florida Department of Transportation (FDOT) will begin milling and resurfacing State Road (S.R.) 776 from the Charlotte County line to south of U.S. 41. FDOT will also begin a median modification project on S.R. 776 from the Charlotte County line to Tangerine Woods Boulevard. While individual project schedules will vary, the combined contract begins in mid-2026 and spans just over 8 miles. Overall project cost is estimated at $15 million. FDOT will provide weekly RoadWatch updates via the project website.

    • Motorists can expect overnight temporary lane closures within the project limits for milling and paving operations on S.R. 776 starting in early July.
    • To keep the road open during construction, motorists can expect crews to work one lane at a time. This may cause uneven pavement on sections of roadway.
    • Crews and equipment may be present within the project limits during daytime hours.
    • Please use caution when traveling through active construction zones and follow posted speed limits.
    • Estimated project completion is summer 2027.