437088-1 SR 78 Sidewalks at Various Locations
Website for Entire Project: http://www.swflroads.com
Project Details
Work Type: | Construction Work |
---|---|
Phase: | Construction |
Limits: | south side of SR 78 from AccessRd to Ben St Chobee St to Lake Drive Linda Rd to Buckhead Ridge RV and Boat Storage |
Length: | 2.001 miles |
County: | |
Road: | |
Construction Cost: | $1.3 million |
Start of Current Phase: | Early 2023 |
Est. Completion of Current Phase: | Mid 2023 |
Public Involvement
Corine Burgess
corine.burgess@ot.state.fl.us
863-241-1459
Contact Information
Design Project Manager |
---|
Ryan Weeks
(863) 519-2837
|
For Media Inquiries Only |
fdot-d1comm@dot.state.fl.us
|
RoadWatch
-
SR 78 Sidewalks at Various Locations: Construction project: Crews will be installing five-foot sidewalks with a retaining wall along the south side of SR 78 from Access Road to Ben Street and from Chobee Street to Lake Drive and from Linda Road to Buckhead Ridge RV & Boat Storage. Other improvements include signing and pavement markings and drainage improvements. During construction daytime lane closures will occur on SR 78. Please use caution in the construction zone and watch for workers in the work zone. Estimated completion is spring 2023.