EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Work Type: New Road
Phase: Planning
City:
County:
Start of Current Phase: Late 2021
About

The Florida Department of Transportation (FDOT) District One has kicked off the much-anticipated Bradenton-Palmetto Connector Alternative Corridor Evaluation (ACE) Study. This ACE study will evaluate feasible corridor alternatives to connect the Cities of Bradenton and Palmetto across the Manatee River and improve regional multimodal mobility, connectivity, and safety for all users, including motorists, bicyclists, pedestrians, trucks and transit.

The need for an improved access across the Manatee River was identified as part of the Central Manatee Network Alternatives Analysis (CMNAA) Study, concluded in 2019, which was a collaboration between FDOT, Manatee County, the Cities of Bradenton and Palmetto, and the Sarasota/Manatee Metropolitan Planning Organization (MPO).

 

* * * 

Study Description

ACE Studies are performed during the Planning phase to define project parameters, the project definition and the purpose and need for the project. The Bradenton-Palmetto Connector Study is part of the Planning phase of the project development process. The study will be used to identify, evaluate, eliminate and recommend project alternatives prior to the Project Development and Environment (PD&E) phase.

Purpose of the Project:

Evaluate additional capacity and transportation demand across the Manatee River as part of the regional transportation system.  Secondary needs of the project are to enhance safety and multi-modal interrelationships.

Need for the Project:

  • Increase roadway capacity
  • Address anticipated transportation demand
  • Increase safety
  • Support modal interrelationships

Study Scope:

  • Phase 1 - Conduct an Alternatives Corridor Evaluation (ACE) Study
  • Phase 2 - Conduct a PD&E Study

The Bradenton-Palmetto Connector Alternative Corridor Evaluation (ACE) Study will evaluate 10 corridors  to address mobility, access and safety concerns including capacity limitations to meet future needs of the area.

The alternatives considered as part of this ACE Study are located in the Cities of Bradenton and Palmetto in west Manatee County.

The ACE Study will document the process for how each of the corridors are evaluated as well as the process used to identify reasonable corridors to advance into the PD&E Study.

As part of this process, the analysis will include a comprehensive evaluation of the natural, social, physical, and cultural environment; project cost; traffic; and the extent to which each corridor meets the purpose and need of this project. Coordination with resource and regulatory agencies, project stakeholders, and the community plays a crucial role in the ACE Study process.

 

Public Involvement

Get Involved

The Bradenton-Palmetto Connector ACE Study has a robust and transparent communication plan in place to truly engage the communities located in the project study area and make sure the study addresses concerns while developing community-sensitive project solutions.

Your feedback plays a critical role during the ACE Study and will direct the project development and decision-making process. We need to know your needs and concerns to determine the best solution for the community. If you would like to submit a comment or ask a question, please click the blue comment box located on the right side of this page. 

PUBLIC INFORMATION MEETING - NOVEMBER 12th (In-person), NOVEMBER 14th (online/virtual)

Bradenton-Palmetto Connector ACE Study in Manatee County

The Florida Department of Transportation (FDOT) invites you to a Public Meeting for the Bradenton-Palmetto Connector ACE Study in Manatee County.

IN-PERSON OPTION:

Tuesday, November 12, 2024

Anytime between 5 -7 p.m.

Manatee County Fairgrounds - Veterans Hall

1402 14th Avenue West, Palmetto, FL 34221

This will include a looping video (no formal presentation) and the project team will be available for discussion.

ONLINE OPTIONS:

Thursday, November 14, 2024

There will be two online option times:

A narrated presentation will be shown at four different times: 11 a.m., 11:30 a.m., 12 p.m., and 12:30 p.m.

A narrated presentation will be shown at four different times: 5 p.m., 5:30 p.m., 6 p.m., and 6:30 p.m.

These events will include a viewing of the project video and a live question-and-answer component with the project team. Please review the materials on project webpage before attending the virtual event (https://www.swflroads.com/project/444843-1). Materials will be posted by Friday, November 8, 2024.

The public meeting is being conducted to present information about proposed corridor alternatives. The meeting will provide the opportunity for the public to express their views about the project. The same materials will be displayed at both the online and in-person events. 

If you are unable to attend the meeting, comments can also be provided through the project webpage (https://www.swflroads.com/project/444843-1) or by email (michelle.rutishauser@dot.state.fl.us) or mail (FDOT District One, Attn: Jimmy Vilce, 801 N. Broadway Ave. MS 1-40, Bartow, FL 33830). While comments about the project are accepted at any time, they must be received or postmarked by Thursday, November 28, 2024, to be included in the formal record. Questions can be answered by calling the FDOT project manager Michelle Rutishauser at (863) 380-7121.

FDOT solicits public participation without regard to race, color, national origin, age, sex, religion, disability, or family status. People who require special accommodations under the Americans with Disabilities Act or who require translation services (free of charge) should contact Cynthia Sykes, District One Title VI Coordinator, at (863) 519-2287, or email at Cynthia.Sykes@dot.state.fl.us  at least seven days prior to the workshop.

The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried out by FDOT pursuant to 23 U.S.C. §327 and a Memorandum of Understanding dated May 26, 2022 and executed by FHWA and FDOT.

This planning project may be adopted into the environmental review process, pursuant to Title 23 U.S.C. § 168, or the state project development process.

 

 

 

FAQs

1. What is an ACE Study?

An Alternative Corridor Evaluation (ACE) Study is a planning process that identifies and evaluates corridors to recommend feasible alternatives that should move forward for additional analysis for compliance with the National Environmental Policy Act (NEPA). ACE Studies take place during the planning phase of a project to determine the systems level planning and analysis and gather all the information needed to transition into individual project solutions and ultimately project programming and funding for design, right-of-way, and construction. The information gathered and analysis made during the ACE Study allows the project to transition into a Project Development and Environment (PD&E) Study, which evaluates the location and conceptual design of feasible alternatives that satisfy the project's purpose and need and their social, cultural, economic and environmental effects following the public hearing, a recommended alternative which includes the no build option will be selected.

Steps in an ACE Study:

  • Identify Corridors
  • Draft Purpose and Need Statement – Why do we need the project?
  • Evaluate Corridors
    • Is it consistent with Local Agency’s Long Range Transportation Plans?
    • Is it consistent with City/County Comprehensive Plans?
    • What are the potential impacts to the environment?
      (Social, Natural, and Cultural)
    • How well does the corridor improve safety and mobility?
    • What is the project cost?
  • Eliminate corridors with significant impacts
  • Recommend Corridors
    • Consistent with Purpose and Need Statement
    • Move forward to PD&E


2. How does this project relate to Central Manatee Network Alternatives Analysis (CMNAA)?

This ACE Study is a direct outcome of the CMNAA analysis and public outreach, and it will take the next step in evaluating the 10 corridors. This study aims to eliminate certain corridors and recommend others to proceed to a PD&E study.


3. What other FDOT projects are underway in this corridor?

Current Area Projects

  1. 10th Avenue Complete Street Study [FPID: 433142-2]
  2. Palmetto Trails Network PD&E Study [FPID: 444857-1]
  3. Bradenton-Palmetto Connector ACE Study [FPID: 444843-1]
  4. Desoto Bridge PD&E Study [FPID: 442630-1]
  5. Sarasota/Manatee US 41 CMASS [FPID: 440154-1]
  6. US 41 Transit Choices ConOps
  7. US 41 Resurfacing from Edwards Drive to Magellan Drive [FPID: 444612-1]
  8. Cortez Corridor Visioning Plan

https://www.swflroads.com/connectingcommunities


4. Will there be a public meeting?

Yes, there will be an Alternative Corridor Evaluation Public Meeting in Fall 2024.


5. How can I comment on the study?

We welcome your input. Email your comments to us through the link at the top of the page. 

View Factsheet
Contact Information
Planning Project Manager
Michelle Rutishauser
813-380-7121
For Media Inquiries Only
fdot-d1comm@dot.state.fl.us
Project Documents
Project Images
FDOT 5 Step Development Process
Bradenton-Palmetto Connector Corridor Map