Work Type: Resurfacing
Phase: Construction
Limits: south of Coleman Road to CR 542 E (Avenue G NW)
City:
County:
Road:
Construction Cost: $4.5 million
Start of Current Phase: Early 2023
Est. Completion of Current Phase: Late 2023
About

The Florida Department of Transportation is resurfacing Recker Highway from Coleman Road to Avenue G NW in Polk County.  In addition to the improvements listed below, crews will add conduit underground just beyond the project limits, from Avenue G NW to CR 542 (K-Ville Avenue).

  • Mill and resurface the roadway
  • Mill and resurface side street entrances
  • Widen the entrance to Sidney Circle
  • Restripe crosswalks at Avenue G NW, Spirit Lake Road and Coleman Road
  • Upgrade signal equipment
  • Improve Drainage
  • Add additional lighting at intersections
  • Place conduit from SR 542 East to CR 542 West to connect the signals

 

 