Project Details
| Work Type: | Interchange Construction |
|---|---|
| Phase: | Construction |
| Limits: | I-75 (S.R. 93) just north and south of Daniels Parkway (C.R. 876) and Daniels Parkway from east of Danport Boulevard to west of Treeline Avenue |
| City: | |
| County: | |
| Road: | |
| Construction Cost: | $42.8 Million (Approx.) |
About
The purpose of this design project is to address the existing operational deficiencies of I-75 and Daniels Parkway Interchange within Lee County and to accommodate future travel demand projections because of forecasted population and employment growth.
The interchange improvements include Improvements include reconstruction of the Daniels Parkway Interchange (Exit 131) converting it to a Diverging Diamond Interchange (DDI) design, reconstruction of the I-75 ramps, construction of pedestrian and bicycle accommodations through the interchange, installation of new signals at the ramps, and resurfacing of Daniels Parkway through the project area.
How does a DDI work? Learn more by viewing one of the informational videos linked below:
English: https://youtu.be/lcEKPyX9Ypg
Spanish: https://youtu.be/mKs3WNEeEec
What is the estimated schedule for the Construction Phase?
- Estimated Start of Construction Phase: Early 2026
- Estimated Completion of Construction Phase: Summer 2028
Public Involvement
Thank you for attending the Pre-Construction Information Session on January 8, 2026 at Riverside Church!
IF YOU WOULD LIKE TO RECEIVE CONSTRUCTION UPDATES
Please click here to sign up for email updates
If you are looking for information about the Three Oaks Parkway Extension Project that is currently conducting work on Daniels Parkway, west of I-75, please contact:
Kris Cella
Phone: 239-337-1071
Email: kcella@cella.cc
Project website: Home - Three Oaks Parkway Extension
Contact Information
| Communications Team |
|---|
|
FDOT-D1COMM
|
| Construction Project Manager |
|
Jesten Abraham
(863) 519-2889
Jesten.Abraham@dot.state.fl.us
|
| Communications Team |
|
Michaela Zawodny
Michaela.Zawodny@dot.state.fl.us
|
| Communications Team |
|
Brian Bollas
813-262-8549
brian.bollas@dot.state.fl.us
|
| For Media Inquiries Only |
|
fdot-d1comm@dot.state.fl.us
|
RoadWatch
-
I-75 at Daniels Parkway (exit 131) Interchange Improvements: FDOT is reconstructing the I-75 at Daniels Parkway interchange. The interchange improvements include reconstruction of the Daniels Parkway Interchange (Exit 131) converting it to a Diverging Diamond Interchange (DDI) design, reconstruction of the I-75 ramps, construction of pedestrian and bicycle accommodations through the interchange, installation of new signals at the ramps, and resurfacing of Daniels Parkway through the project area.
The following activities are subject to change based on weather conditions and unforeseen underground conditions.
During the nighttime/overnight hours of 9 p.m. to 7 a.m. from Sunday, March 22 through Thursday, March 26, motorists should anticipate lane closures on northbound I-75 for crews to work on temporary roadway construction.
Crews are working on widening and installing a temporary barrier wall at the southbound I-75 off-ramp and Daniels Parkway. Motorists should expect a lane closure on the ramp between the nighttime/overnight hours of 7 p.m. to 7 a.m. on Sunday night, March 22.
Crews are working on earthwork and underground drainage throughout the project area.
Please note that the westbound lanes on Daniels Parkway, west of I-75, are shifted slightly to the south, then back to the north. Traffic on the southbound I-75 off-ramp has also shifted to the east. Please pay attention to signs and pavement marking and drive with caution.
Motorists are advised that the speed limit has been reduced in the project area. Please follow all posted signage.
Pedestrian access has been shifted to the south side of Daniels Parkway. Please follow signs and proceed with caution in the work zone.
Motorists should expect trucks and equipment to be moving materials throughout the project.
When necessary, motorists should anticipate lane closures on I-75 between 9 p.m. and 7 a.m. and on Daniels Parkway between 7 p.m. and 7 a.m., with the exception of three hours before, during and three hours after Spring Training baseball games at Hammond Stadium and Jet Blue Park.
Please use caution and watch for workers and construction vehicles entering and leaving the roadway. The expected completion date is summer 2028. For more information please visit: https://www.swflroads.com/project/446296-2.