Project Details
Work Type: Resurfacing
Phase: Construction
Limits: from north of Transport Road in Bartow to Avenue G SW in Winter Haven
Length: 4.8 miles
City:
County:
Road:
Construction Cost: $7.5 million
Start of Current Phase: Early 2026
Est. Completion of Current Phase: Late 2026
About

This FDOT pavement-only project will enhance ride quality along U.S. 17, beginning just north of Transport Road in Bartow, continuing through Eagle Lake, and ending at Avenue G SW in Winter Haven. Work includes milling and resurfacing, along with minor sidewalk repairs to bring facilities into compliance with current ADA standards.

Rumble strips will also be installed along the roadway edge lines through Eagle Lake to improve safety by providing audible and tactile alerts for drivers who drift out of their lane.

Lane closures on U.S. 17 will be restricted to nighttime hours, from 7 p.m. to 7 a.m., to minimize daytime impacts. Pedestrians should anticipate minor detours while sidewalk repairs are underway.

View Factsheet
Contact Information
Communications Team
Sandra Mancil
863-519-4116
Sandra.Mancil@dot.state.fl.us
For Media Inquiries Only
fdot-d1comm@dot.state.fl.us
RoadWatch
  • Expect nighttime/overnight lane closures Sunday through Thursday nights as crews continue milling and resurfacing, weather permitting. Use caution and be prepared to merge.

Project Videos
Project Images
Machine Spreading Tack Before Paving on 01-21-26
Paving Machine Places Asphalt on 01-21-26
Workers Smooth Asphalt Before the Roller Compacts it on 01-21-26
Rolling Machine Compacts Newly Placed Asphalt on 01-21-26
Milling Machine Removing Asphalt on US 17 on 01-21-26
Rolling the newly paved asphalt on U.S. 17 on January 12, 2026
Paving new asphalt on U.S. 17 on January 12, 2026
Machine milling the roadway on U.S. 17 on January 12, 2026