Project Details
Work Type: Safety Project
Phase: Construction
Limits: 15th Street E (SR 70 spur) from 30th Avenue East to 26th Avenue East
Length: 0.25 miles
City:
County:
Construction Cost: $1.3 million
Start of Current Phase: Mid 2026
Est. Completion of Current Phase: Late 2026
About

The improvements for this project consist of milling and resurfacing, sidewalk, drainage, lighting, and signalization on 15th St E (SR 70 spur) from 30th Avenue E to 26th Avenue E in Manatee County.

View Factsheet
Contact Information
Communications Team
Barbara Catlin
941-302-5048
barbara.catlin@dot.state.fl.us
Communications Team
Nancy Morgan
941-720-6335
Nancy.morgan@dot.state.fl.us
For Media Inquiries Only
RoadWatch
  • 15th Street E (S.R. 70 Spur) from 30th Avenue E to 26th Avenue E: Construction project: The Florida Department of Transportation (FDOT) is milling and resurfacing 15th Street E (S.R. 70 Spur) from 30th Avenue E to 26th Avenue E in Manatee County. This safety project’s improvements also include installation of new sidewalk and existing sidewalk repairs, drainage work, lighting, signalization, signage and new pavement markings on approximately .25 miles.

    • Motorists can expect intermittent daytime and nighttime lane closures throughout the project limits.
    • Please be aware there may be uneven areas of pavement while work is underway.
    • Pedestrians can expect detours where sidewalks are being repaired or replaced.
    • Please follow signage and watch for workers in and near the roadway during daytime and nighttime hours.
    • The estimated completion is fall of 2026.