Project Details
Work Type: Resurfacing
Phase: Construction
Limits: S.R. 64 from W of C.R. 675 (Rutland Road) to Wingate Road
Length: 10.9 miles
County:
Road:
Construction Cost: $8.3 Million
Start of Current Phase: Late 2026
About

The Florida Department of Transportation (FDOT) will begin milling and resurfacing  S.R. 64 from west of C.R. 675 to Wingate Road in Manatee County. The improvements consist of milling and resurfacing, drainage, curb and gutter, signing and pavement markings. This project spans  approximately 10.9 miles in length with an estimated cost of $8.3 million.

View Factsheet
Contact Information
Communications Team
Nancy Morgan
941-720-6335
Nancy.morgan@dot.state.fl.us
Communications Team
Barbara Catlin
941-302-5048
barbara.catlin@dot.state.fl.us
For Media Inquiries Only
RoadWatch
  • The Florida Department of Transportation (FDOT) will begin milling and resurfacing  S.R. 64 from west of C.R. 675 to Wingate Road in Manatee County. The improvements consist of milling and resurfacing, drainage, curb and gutter, signing and pavement markings. This project spans  approximately 10.9 miles in length with an estimated cost of $8.3 million.

    • Motorists can expect temporary daytime/overnight  lane closures throughout the project limits.
    • Motorists can expect workers and construction equipment during daytime /overnight hours.
    • Motorists can expect uneven lanes during the milling and paving operations.
    • Expected completion is spring of 2027, weather permitting.