Work Type: Construction Work
Phase: Construction
Limits: From south of Pinegrove Circle to north of Washington Loop Road
Length: 2.095 miles
City:
County:
Road:
Construction Cost: $7.4 Milion
Start of Current Phase: Mid 2026
Est. Completion of Current Phase: Mid 2027
About

The improvements under this contract include milling and resurfacing, base work, and shoulder treatment, along with drainage enhancements. Additional work consists of the installation and reconstruction of curb and gutter, guardrail, sidewalks, bridge joints, traffic railing, lighting, signage, and pavement markings. These improvements will be carried out along State Road 35 (US 17), extending from south of Pinegrove Circle to north of Washington Loop Road in Charlotte County.

FAQs

During construction, motorists should expect daytime and nighttime/overnight lane closures. Motorists are asked to exercise caution and reduce their speed while driving through the work zone. The construction schedule may change due to weather or other unexpected conditions.