Project Details
Work Type: Interchange Construction
Phase: Construction
Limits: I-75 (S.R. 93) at Toledo Blade Boulevard (Exit 179) and I-75 at Sumter Boulevard (Exit 182)
City:
County:
Road:
Construction Cost: $13.4 Million
Start of Current Phase: Early 2026
Est. Completion of Current Phase: Mid 2027
About

FDOT is making improvements to the I-75 at Toledo Blade Boulevard and I-75 at Sumter Boulevard interchanges in Sarasota County, Florida.

452356-1: Sumter Boulevard 

The I-75 interchange at Sumter Boulevard project includes the installation of signals at both ramp connections. The improvements include signals, controlled pedestrian cross walks, intersection lighting and adding a northbound I-75 free flow on-ramp from southbound Sumter Boulevard. The improvements also provide dual left turn lanes from northbound Sumter Boulevard onto northbound I-75. Sumter Boulevard is an arterial under the jurisdiction of the City of North Port.

452357-1: Toledo Blade Boulevard

The I-75 interchange at Toledo Blade Boulevard project includes the installation of signals at both ramp connections. The improvements include signals, controlled pedestrian cross walks, intersection lighting and adding a northbound I-75 free flow on-ramp from southbound Toledo Blade Boulevard. The improvements also provide dual left turn lanes from northbound Toledo Blade Boulevard onto northbound I-75. The completed project includes widening of the northbound lanes to provide 2 full lanes through the Toledo Blade Boulevard interchange. Toledo Blade Boulevard is an arterial under the jurisdiction of the City of North Port.

Public Involvement

Thank you for attending the Pre-Construction Information Session on January 6, 2026 at Suncoast Technical College - North Port Branch!

 

IF YOU WOULD LIKE TO RECEIVE CONSTRUCTION UPDATES

Please click here to sign up for email updates

View Factsheet
Contact Information
Communications Team
Construction Project Manager
Jesten Abraham
(863) 519-2889
Jesten.Abraham@dot.state.fl.us
For Media Inquiries Only
RoadWatch
  • I-75 at Toledo Blade Boulevard (exit 179) and Sumter Boulevard (exit 182) Interchange Improvements: FDOT is making improvements to the I-75 at Toledo Blade Boulevard and I-75 at Sumter Boulevard interchanges. Improvements for both interchanges include the installation of signals at both ramp connections, controlled pedestrian crosswalks, intersection lighting, and the addition of northbound I-75 free flow on-ramps from southbound Toledo Blade Boulevard and from southbound Sumter Boulevard. In addition, northbound lanes will be widened to provide two full lanes through the Toledo Blade Boulevard interchange. At the Sumter Boulevard interchange, dual left turn lanes will be added from northbound Sumter Boulevard onto northbound I-75. 

     

    The following activities are subject to change based on weather conditions and unforeseen underground conditions. 

      

    • Crews will be working on erosion control, conduit installation, and prep work for drilled shaft installation.  

     

    • When necessary, motorists should anticipate lane closures on the I-75 ramps between 10 p.m. and 4 a.m. and full ramp closures between 11 p.m. and 5 a.m. Single lane closures on Sumter Boulevard and Toledo Blade Boulevard can be expected from 9 a.m. to 4 p.m. as well as 7 p.m. to 7 a.m., and double lane closures from 8 p.m. to 6 a.m. 

     

    Please use caution and watch for workers and construction vehicles entering and leaving the roadway. The expected completion date is early 2027. For more information please visit: https://www.swflroads.com/project/452356-1.  

     

     