430204-2 Cortez Bridge Project
Project Details
| Work Type: | Bridge Construction |
|---|---|
| Phase: | Construction |
| Length: | 0.9 miles |
| City: | |
| County: | |
| Road: | |
| Construction Cost: | $123M |
About
The Florida Department of Transportation (FDOT) District One begins construction on the Cortez Bridge on State Road (SR) 684 in Manatee County, Florida. The project includes the bridge and roadway approaches from SR 789 (Gulf Drive) to 123rd Street West, a distance of about 0.9 mile.
Construction Overview
The bridge replacement project will be built in two phases to maintain traffic throughout construction. During Phase 1, crews will construct the northern half of the new bridge alongside the existing bridge. Once completed, traffic will be shifted onto the new bridge, allowing Phase 2 to begin. Phase 2 includes demolition of the existing bridge and construction of the remaining portion of the new bridge. Construction will be performed using barges and temporary trestles in both phases.
RoadWatch - November 22 - November 28
SR 684 (Cortez Road) Bridge Replacement Project from Gulf Drive (S.R. 789) to 123rd Street West: Construction project: The project includes replacing the existing bridge and improving roadway approaches between Gulf Drive (S.R. 789) and 123rd Street West, approximately 0.9 miles. Construction will occur in two phases to maintain traffic throughout the duration of the project. Phase 1 consists of constructing the northern half of the new bridge adjacent to the existing structure. Upon completion, traffic will be shifted onto the new bridge, allowing demolition of the existing bridge and construction of the southern half during Phase 2.
- Work operations will be suspended from Thursday, 11/26/26, through Sunday, 11/29/26 for the Thanksgiving Holiday.
- The contractor is performing pile-driving operations, force main work along Hunters Point Way, constructing temporary roadway diversions on each side of the bridge, installing temporary striping and barrier wall, and installing erosion control measures.
- Motorists should expect intermittent daytime and nighttime closures throughout the project limits as construction activities progress.
- Nighttime closures are expected for crews to place temporary striping and barrier walls.
- Periodic shoulder closures and temporary traffic pattern shifts may be necessary to accommodate construction operations.
- Marine traffic will be maintained throughout construction, and the current drawbridge opening schedule will remain in effect.
- Construction activities are scheduled between 7 a.m. and 6:30 p.m.; however, some nighttime and weekend work may be required.
- Motorists, pedestrians, and bicyclists should use caution and watch for construction vehicles entering and exiting the work zone.
- Please use caution and follow all posted signage while traveling through the project area.
- The anticipated completion date is summer 2030. For more information, please visit www.SWFLRoads.com/project/430204-2.
Project Cost and Schedule
- Construction Cost: Approximately $123 million
- Construction Duration: Approximately 1,200 days
- Phase 1 Traffic Shift: Anticipated by the end of this year
- Phase 2 Traffic Shift: Anticipated in mid-2028
The phased construction approach is designed to minimize disruptions while delivering a new bridge and associated roadway improvements.
A Bridge Aesthetics Committee (BAC) was formed during the design phase of the project consisting of community representatives from Cortez and Bradenton Beach to provide input on the bridge aesthetics.
BAC Members included (at the time):
Joe Adorna (Cortez Park), Mike Bazzy (Bradenton Beach Marina), Karen Bell (Tide Tables), Mayor John Chappie (Bradenton Beach), David Galuska, Connie Morrow (Runaway Bay & Mariners Cove), Ann Marie Nichols (Room with a Hue), Joe Rogers (Seafood Shack), Jeff Vey (Bridgeport Condos), Gloria Weir (Cortez Park), and Bobby Woodsen (Tide Tables).
BAC Meetings and Additional Small Group Meetings during Design: August 12, 2020; January 6, 2021; January 20, 2021; February 10, 2021; March 1, 2021; March 10, 2021; April 1, 2021; April 22, 2021; May 27, 2021; November 9, 2021 and May 3, 2024. Future meetings will be scheduled as needed.
To date, the BAC has determined the following (may be altered in final design)
- Preference is for aesthetically enhanced multi-column pier with a waterline footing. The exterior face of the column would be in line with the exterior face of the bridge deck. Cheekwalls would extend from the top of the pier to the underside of the deck at all pier locations.
- Preference is for four overlooks, located on the north and south side of the bridge at the two piers on either side of the main channel.
- Preference for substructure lighting on the exterior faces of the pier columns.
- A custom “wave” infill pattern is suggested for the bridge pedestrian railings.
Public Involvement
The Florida Department of Transportation (FDOT) held a Pre-construction Public Information Session for the Cortez Road (SR 684) Bridge Replacement Project in Manatee County. The meeting was held on Tuesday, October 20, 2026 at the Kirkwood Church located at 6101 Cortez Road West, Bradenton, FL 34210
This information session was an open house format held from 4 - 6 p.m., and the project team was available for discussion. The Pre-construction Public Information Session was conducted to share information about construction activities and traffic phasing.
Click the link below to sign up for email updates:
https://www.emailmeform.com/builder/form/5I7k4f0Lf2ardR3i0QMW
The Florida Department of Transportation (FDOT) hosted a design public meeting on January 31, 2023.
The materials were available at the design public meeting: project presentation (video and slides), display boards, bridge 3D animation, and handouts (comment form and newsletter). You may access these files in the Project Documents and Project Videos sections below.