Project Details
| Work Type: | Interchange Construction |
|---|---|
| Phase: | Construction |
| Limits: | Along Pine Ridge Road from west of I-75 to east of I-75 |
| Length: | 0.5 miles |
| City: | |
| County: | |
| Road: | |
| Construction Cost: | $27.5 million (Approximate) |
| Start of Current Phase: | Early 2025 |
| Est. Completion of Current Phase: | Mid 2027 |
About
I-75 at Pine Ridge Road interchange is one of the four interchanges along I-75 in Collier County. This project has been advanced as a part the Moving Florida Forward Infrastructure Initiative.
The interchange improvements include the construction of a Diverging Diamond Interchange (DDI), which will significantly reduce delay on Pine Ridge Road, and reduce the number of conflict points to improve overall safety for all users. The DDI also offers the ability to accommodate future traffic volume growth. This project has been advanced as a part the Moving Florida Forward Infrastructure Initiative.
Improvements include:
- Reconstruction of the Pine Ridge Road Interchange converting it to a Diverging Diamond Design
- Reconstruction of the interchange on and off ramps
- Construction pedestrian and bicycle accommodations through the interchange
- Installation new signals at the ramps
- Resurfacing Pine Ridge Road through the project area
How does a DDI work? Learn more by viewing one of the informational videos linked below:
English: https://youtu.be/lcEKPyX9Ypg
Spanish: https://youtu.be/mKs3WNEeEec
Public Involvement
Thank you for attending the Pre-Construction Information Session on Tuesday, February 18, 2025 at North Collier Regional Park!
IF YOU WOULD LIKE TO RECEIVE CONSTRUCTION UPDATES
Contact Information
RoadWatch
-
I-75 at Pine Ridge Road (exit 107) Interchange Improvements: FDOT is reconstructing the I-75 at Pine Ridge Road interchange. The interchange improvements include reconstruction of the Pine Ridge Road Interchange converting to a Diverging Diamond Interchange (DDI) design, reconstruction of the interchange on and off ramps, construction of pedestrian and bicycle accommodations through the interchange, installation of new signals at the ramps, and resurfacing of Pine Ridge Road through the project area.
The following activities are subject to change based on weather conditions and unforeseen underground conditions.
On Friday, May 29 from 7 p.m. to 11 p.m. there will be intermittent closures of the southbound I-75 on-ramp and northbound I-75 off-ramp. Motorists should follow the posted detour signs or identify alternate routes.
From Friday, May 29 at 11 p.m. to Monday, June 1 at 6 a.m. there will be a full closure of eastbound and westbound Pine Ridge Road under I-75 for motorists, pedestrians, and cyclists.
The following movements will be closed:
Eastbound and westbound Pine Ridge Road, under I-75
Left turn from northbound I-75 off-ramp to westbound Pine Ridge Road
Left turn from southbound I-75 off-ramp to eastbound Pine Ridge Road
- During this closure, motorists should follow posted detour routes. For southbound I-75 to eastbound Pine Ridge Road, motorists may exit at Immokalee Road (Exit 111) eastbound to southbound Logan Boulevard, then return to Pine Ridge Road. For northbound I-75 to westbound Pine Ridge Road, motorists may exit at Golden Gate Parkway (Exit 105) westbound to northbound Livingston Road, then return to Pine Ridge Road. I-75 will remain open in both directions over Pine Ridge Road.
- Motorists traveling east on Pine Ridge Road may enter southbound I-75, exit at Golden Gate Parkway, enter northbound I-75, and exit onto eastbound Pine Ridge Road. Motorists traveling west on Pine Ridge Road may enter northbound I-75, exit at Immokalee Road, enter southbound I-75, and exit onto westbound Pine Ridge Road.
- Please follow the posted detour signs or identify alternate routes and exercise caution through the detour area and anticipate delays.
Crews will be working on paving, drainage installation, roadway work, pond excavation, and underground utilities.
Motorists should anticipate lane closures on Pine Ridge Road during the nighttime/overnight hours of 7 p.m. to 7 a.m., and ramp closures from 8 p.m. to 6 a.m. Please use extra caution when driving through this area and expect delays.
Crews will be working on clearing and grubbing and installing erosion control throughout the project area.
Please use caution and watch for workers and construction vehicles entering and leaving the roadway. The expected completion date is mid-2027. For more information please visit: https://www.swflroads.com/project/445296-1.